Permits can feel like red tape, but they exist to make sure electrical work is inspected and safe. Xlectrical pulls electrical permits throughout Broward County and in nearby Palm Beach cities. Here is how it works city by city: who issues the permit, which online portal each city uses, how long review takes, and what changed in 2026.
In Broward County, electrical work needs a permit from the city where the property is located, or from Broward County for unincorporated areas. Electrical work still needs a permit even under Florida's 2026 $7,500 permit exemption (HB 803). In our experience, permit review takes about 7 to 30 days depending on the city, and cities that still handle paper permits tend to be slower.
Does the $7,500 permit exemption (HB 803) apply to electrical work?
No. Florida's HB 803, signed on May 7, 2026 and in effect since July 1, 2026, exempts certain residential construction work valued under $7,500 from a building permit. The exemption does not apply to electrical, plumbing, structural, mechanical or gas work, or to property in a flood hazard area, so panel changes, new circuits, EV chargers and generator hookups still need an electrical permit. Cities also say the exemption is not automatic: Fort Lauderdale, for example, asks owners to submit a Residential Permit Exemption Request form, and splitting a larger project into smaller ones to avoid a permit is not allowed. Sources: Florida Senate bill summary, City of Fort Lauderdale HB 803 guide, City of West Palm Beach permits FAQ.
Who issues the permit?
Broward County has 31 municipalities, and most have their own building department. Properties in unincorporated Broward County (the Broward Municipal Services District) are permitted through the Broward County Building Code Division. Before applying, confirm the jurisdiction for the address with the Broward County Property Appraiser. Electrical work in Florida must meet the Florida Building Code, which adopts the National Electrical Code.
Electrical permits by city
Each city runs its own online portal. This table summarizes what each building department publishes. Portals and forms change, so check the city's page before applying.
| City | Online portal | What to know | Building department |
|---|---|---|---|
| Sunrise | Self-Service Portal (Open for Business) | Electrical permits use the Broward County Uniform Building Permit Application plus the City of Sunrise Electrical Addendum. Inspections can be scheduled online or by phone by 3 pm the day before. | Building Division, (954) 572-2354 |
| Fort Lauderdale | LauderBuild | Paper applications have not been accepted for new submissions since January 1, 2024. Service changes follow the city's Electrical Service Permit Checklist (plans, load calculation, riser diagram). Our Fort Lauderdale permit guide → | Development Services |
| Plantation | Online Permitting | The city requires electrical permits for all electrical work, including new service equipment, service relocations, service increases and fixed equipment connections. | Building Department, (954) 797-2765 |
| Weston | ePermits | Uses the Broward County Uniform Building Permit Application plus an Electrical Permit Application; some jobs need load calculations and a riser diagram. Applications are signed and notarized for each discipline. | Building Code Services, 954-385-0500 |
| Coral Springs | eTRAKiT | Since January 1, 2026 the Building Department no longer processes paper permits. Inspections are scheduled online. | Building Department, 954-344-1025 |
| Davie | eSuite | Contractors need an online account to submit permits. | Town of Davie eSuite |
| Pompano Beach | Online application and electronic plan review | One building permit application covers electrical work. Electrical inspections typically include underground, rough and final stages. | Building Inspections |
| Parkland | My Government Online (MGO) | MGO replaced the city's previous permitting software, and contractors re-registered there. Electrical service change checklists include load calculations. | Building Division, 954-753-5447 |
| Southwest Ranches | Broward ePermits | Building permit services are provided for the town by a contracted provider. Applications are signed and notarized for each discipline, and some permits need zoning or engineering approval first. | Building Permitting and Inspections |
| Unincorporated Broward | Broward County ePermits | Contractors must be registered with the county. ePermits is not available for owner-builder permits. Some permits, such as meter releases, service changes and minor electrical repairs, can be obtained walk-through. | Broward County Building Code Division |
Nearby Palm Beach County cities
| City | Online portal | What to know | Building department |
|---|---|---|---|
| Boca Raton | Boca eHub (applications) and Boca ePlans (plan files) | A registered eHub account is needed to apply or request inspections. | Building Permits and Inspections, 561-393-7930 |
| West Palm Beach | Civic Access (EPL) | Fully digital: apply, pay, resubmit plans and schedule inspections. The city states electrical work needs a permit regardless of cost. | Building Division, (561) 805-6700 |
| Boynton Beach | SagesGov | Paperless: all submittals are uploaded as PDFs. Inspections are requested by 3 pm the day before. | Building Division |
| Lake Worth Beach | Online permit search and inspection scheduling | Check with the Building Division for current online application options. | Building Division, (561) 586-1647 |
Source: each city's building department website, reviewed November 2026.
How long does an electrical permit take?
From our experience pulling permits across Broward County, plan review for an electrical permit usually takes about 7 to 30 days, depending on the city and the scope. Cities that still rely on paper permits tend to be slower than cities with fully online systems. In general, we find Broward and Palm Beach County cities faster than Miami-Dade. Simple jobs move faster than service upgrades that need load calculations, riser diagrams or utility coordination with FPL.
Work that typically needs a permit
- Electrical panel replacements of any size, whether or not the amperage changes, and service upgrades
- New circuits, including dedicated circuits for EV chargers, appliances and equipment
- Standby generators and transfer switches
- Remodels, additions and new construction wiring
- Pool, spa and many outdoor electrical installations
Small like-for-like repairs, such as replacing a damaged receptacle or switch, may not require a permit — but the rules differ between jurisdictions.
How the process works
- Application: the licensed contractor submits the permit with the scope of work (and plans or load calculations when required).
- Approval: the building department reviews and issues the permit.
- Inspections: larger projects may have a rough-in inspection before walls are closed and a final inspection at the end. Service changes also involve coordination with the utility.
- Closeout: once the final inspection passes, the permit is closed.
Why unpermitted work causes problems
- It hasn't been inspected for safety.
- It can complicate insurance claims and 4-point inspections.
- Open or missing permits often surface when you sell the home.
Can homeowners pull their own permit?
Florida law (section 489.503, Florida Statutes) allows an owner to do their own electrical work on a single-family home or duplex for their own use, not for sale or rent, under an owner-builder permit. The owner signs a disclosure statement and takes on full responsibility for the work and inspections. Commercial electrical work requires a licensed contractor, and in unincorporated Broward the county's ePermits system does not accept owner-builder permits. For most electrical projects, hiring a licensed electrical contractor is the safer path.
Common questions
Do I need a permit to replace an electrical panel in Broward County?
Yes. Panel replacements in general need an electrical permit, whatever the amperage, as do service upgrades. The permit comes from your city, or from Broward County in unincorporated areas, and they are inspected before the utility restores power.
Does Florida's $7,500 permit exemption cover electrical work?
No. HB 803 (2026) exempts some residential work under $7,500 from a building permit, but electrical, plumbing, structural, mechanical and gas work still need permits.
How long does an electrical permit take in Broward County?
In our experience, plan review takes about 7 to 30 days depending on the city. Cities with fully online systems tend to be faster than cities that still handle paper permits.
Do I need a permit to install an EV charger?
Yes. A Level 2 charger needs a new 240V circuit, which requires an electrical permit and inspection.
Digital permit drawings, not hand sketches
What sets Xlectrical apart from many contractors is how we prepare permit submittals. Our drawings and documents for the city are designed digitally, while many contractors still submit hand-drawn sketches. Clean digital drawings are easier for plan reviewers to read and fit the online portals most Broward and Palm Beach cities now require.